Sprint 2 – Sprint Retrospective – Actual

Velocity for this Sprint: 
4 ideal days.

Sprint Backlog items completed:

Phoenix::Project Manager::Print Costs Estimator::Save estimates to the database

Sprint Backlog items not completed:

  1. Phoenix::Project Manager::Print Costs Estimator::Coordinate documentation of requirements
  2. Phoenix::Project Manager::Print Costs Estimator::Design and functionality revisions
  3. Phoenix::Project Manager::Print Costs Estimator::Final web form layout (with Phoenix wrapper)
  4. Mercury::Add Amazon (basic, no exclusions)
  5. Mercury::Add Amazon exclusions

Completed items accurately estimated:

N/A

Completed items under- estimated:

[1] Phoenix::Project Manager::Print Costs Estimator::Save estimates to the database [4 ideal days]

Scope change – unplanned required features not in the original estimate:

  1. [1 ideal days] NAXchange::Print Costs Estimator::Design and functionality revisions.
  2. [.25] Phoenix::Project Manager::Print Costs Estimator::Save estimates to the database::Generate an estimate_id.
  3. [.25] NAXchange::Print Costs Estimator::Attach a PDF of the current estimate to email notifications.